PDX Gate D10 and D11 Sterile Corridor Improvements

As part of CHA’s On-Call services contract with the Port of Portland, we upgraded the Concourse D International Flight Gate areas of to comply with the Department of Homeland Security – Customs and Border Protection, current design standards as well as the Port’s common use standards. The work included several fully glazed partition walls to replace existing folding partitions connecting these gates to the Federal Inspections Services area, as well as new millwork, data system upgrades, flight information display replacement, new ceilings and flooring, as well as full CCTV coverage of the corridors, holdrooms, the jet bridges, and ramp areas. The project was a collaborative effort between Department of Homeland Security – Customs and Border Protection and the Port of Portland.